JML EXPO METRO 
INTERNAL CLADDING'S FRAME & BRACKETS 

2019.09.08 Kick-off Meeting in JML office

CONFIRM TO START THE WORK BY JML
Contract Pending
Downpayment Issued
 

2019.09.09-2019.09.11 Initial 3d Model

80% Bracket 70% Framing
Contract Pending
Downpayment Issued
Progress Payment Issued
 

2019.09.12

Meet JP and review the 3d works.
JP provides the new cladding bracket layout (orange bracket).
2019.09.13-2019.09.20 Revised 3d Model Rev.01
95% Bracket 90% Framing
Contract Pending
Downpayment Pending
Progress Payment Pending
 

2019.09.22

Meeting with
Jaypee/Diomel/Antony/Ashraf

Review the 3d works

Diomel will provide the new details where the interface with concrete.
Diomel will provide the extra connection or bracing aluminum tube
Contract Pending
Downpayment Pending
Progress Payment Pending
 

2019.09.28

Final 3d works awaiting approval/comments
Expected by 29Sep2019.
Please indicate required details for concrete interface/the extra steel bracket or more alum bracing.
Contract Pending
Downpayment Pending
Progress Payment Pending
Invoice updated pending from HAE
Invoice Confirmation pending from JML
 

2019.09.29

Antony provides the comment in PDF/DWG
Pending required details for the interface to concrete (Anchor bolt/base plate)
Contract Pending
Downpayment Pending
Progress Payment Pending
Invoice submitted

Folders from links at right

JML2HAE

Files From JML to HeroesAE

HAE2JML

Files From HeroesAE to JML