A01. EBOT - 1st Fire Extinguisher Robot for Exterior of Buildings in the world

A02. EBOT - Introduction Video

A03. EBOT - UAE BUILDINGS

Dubai Market Analysis As Below

A04. EBOT - GLOBAL HIGHRISE BUILDINGS

Global market as below …

B01. EBOT - UAE Agent - Meeting - 18May

Agent Attendance: Mr.David

B02. EBOT - UAE Agent

Required Documents to be sent to Email: team@heroesae.com
1, Brief Introduction of Agent and the Team
2, Passport Copy
3, NDA (Non Disclosure Agreement)
4, Business Plan from Agent of UAE Market & Global Market.

SCHEDULE OF EBOT PROJECT

Below schedule is the initial version of ebot works
5.19

Ebot MOA with Agent

Ebot-R101
5.19-5.30

Business Development

Estimated Ebot Sales Amount as Below List
6.1-6.15

MOU from Target Clients ( EMAAR or Other Clients)

Memorandum of Understandingfrom Target Clients from Agent
6.23

Ebot Frame Agreement

Ebot-R101 laboratory test
6.25

Down Payment for Ebot 10-20 Sets

25% Payment to Heroes Architects & Engineers & Agent
6.25

Ebot-R101 Customized Design As per Client Buildings

Including Software and Hardware design and fabrication
8.25

Ebot-R101 Delivery On Site

Including Logistics and Storage
8.30

Ebot-R101 Installation & Test

Ebot will be installed and tested, paid by client for installation.
9.15

Ebot Test Report 1st Circle 15 days

Normally first test circle will be 15days
9.30

Ebot-R101 Report and Review

-
10.1

Ebot Progress Payment

50% of payment to Heroes Architects & Engineers & Agent
10.1-11.30

Ebot Running Track

Daily tracking at the first month, weekly tracking at the second and third months.
every 30 days

Ebot Regular Maintenance

Enter a description

C01. EBOT - HAE Responsibility

Ebot-R101: Development, Fabrication, Building Modelling, Building Analysis
  • Including Software/Hardware/Engineer/Materials/Chips/Logistics/Storage/Replacement/workman ship/etc.
  • Maintenance Fee should paid by clients, the fee will be varies due to complex of building.

C02. EBOT - Agent Requirement

Ebot-R101 Sales Price: Dhs500,000 - Dhs1,000,000 as per complicity of the buildings
Agent should achieve the target as below list
Agent to built up his sales team
Fail to achieve the target will affect the profit sharing for agent
Enage with the clients
Business plan for the sales of Ebot

C03. EBOT - Profit Sharing

Agent share 15%-25% from gross profit.
Agent will invest on the sales team and ensure the sales increasement.
All payment through HAE bank account and HAE will issue the payment to Agent within 5 working days.
YearTarget SalesUnitSales IncreasingAgent ProfitUnit
201950Sets 3,750,000 AED
2020200Sets300% 15,000,000 AED
2021500Sets150% 37,500,000 AED
20221000Sets100% 75,000,000 AED
20231800Sets80% 135,000,000 AED
20243000Sets67% 225,000,000 AED
20254500Sets50% 337,500,000 AED
20266000Sets33% 450,000,000 AED
20277500Sets25% 562,500,000 AED
20289000Sets20% 675,000,000 AED
© 2023 Heroes Architects & Engineers Co. Ltd. All rights reserved.